Contact Us:
1300 88 16 88

Resident’s Page

Welcome to the Banbury Village residents page where purchers can find out useful information regarding the development, the handover process and their new home.

Civil construction of the western portion of the estate is complete and construction of many of the homes at Banbury Village is well under way. An outline of the current key dates is as follows
:

Please note that these dates are estimates and may vary.

For more information regarding construction progress please visit Chris' Blog.

Please note that these dates are estimates and may vary.

For more information regarding construction progress please visit Chris' Blog.

Stages

Lots

Expected Construction Commencement

Expected Settlement

1

12-14, 54-60

Complete

Complete

2

101-109, 201-209

Complete

Complete

3&5

61-67, 15-17

Complete

Complete

6

301-315

Complete

Complete

4

121-132

Complete

Complete

7 601-609, 701-709 Complete Complete
8 18-26 Complete Complete

9

68-79, 87-92 Underway March 2012

10

133-135, 143-146 Underway April 2012

H1

Apartments, T/Houses Underway April 2012
H2 Apartments Underway August 2012